Slyfield iwmc

Non technical Summary

On behalf of

Thames Waste Management

 

July 2000


1.       introduction

1.1     Thames Waste Management (TWM) are submitting a planning application for the construction of an Integrated Waste Management Centre (IWMC) comprising an Energy from Waste [EfW] plant, a materials recycling facility [MRF] and civic amenity site [CA site] on land at the Slyfield Industrial Estate, Guildford.

1.2               This statement sets out in non-technical language a summary of the Environmental Impact Assessment that accompanies that application.

2.       development context

Introduction

2.1     The application site lies at the eastern end of the Slyfield Industrial Estate, on the northern outskirts of Guildford. To the west is the residential area of Slyfield Green and to the east the River Wey, with the A3 beyond. The Guildford sewage treatment works (STW) lies immediately to the south with land directly to the north being a former landfill site.

2.2     The application site is owned partly by Thames Water (TW) and partly by Surrey County Council (SCC). The SCC land is occupied by a waste transfer station and civic amenity site. The TW land is vacant and used only for the management of sewage sludge and the disposal of stormwater from the STW. Access to both sites is off Moorfield Road. This forms a junction with the A320 Woking Road.

2.3     The TW land is allocated for employment use within the deposit draft of the Guildford Borough Local Plan.

The Proposed Development

2.4     The development will consist of three main parts:

 

§                     An Energy from Waste (EfW) plant;

§                     a Materials Recycling Facility (MRF); and

§                     a civic amenity facility (CA site) to replace the existing.

 

There will also be a weighbridge and office together with roads and extensive landscape planting. The layout of the site is shown on Figure 2.3.


Energy from Waste

2.5     The EfW plant has been designed to treat up to 225,000 tonnes of household waste a year as part of the Surrey Waste Management contract. It will consist of:

 

§                     a waste reception hall with six reception bays linked to a storage bunker;

§                     a central control room;

§                     a two stream grate within which the waste is burnt;

§                     a steam turbine and electric alternator to produce the electricity;

§                     a two stream gas cleaning system to remove pollutants from the gas given off during burning;

§                     a 70 metre high stack (chimney) to disperse gases to the atmosphere; and

§                     condensers to cool the exhaust steam and turn it back to water for re-use in the plant.

 

2.6     The way in which the plant operates is shown in Figure 2.4.

2.7     Two residues come from the incineration process;

 

§                     Bottom Ash, of which there will be about 67,500 tonnes a year and which comes from the burning of the waste. This material can be recycled as construction materials; and

§                     Fly Ash which comes from the filters used to clean the gas. This amounts to about 13,500 tonnes a year. It is removed in sealed tankers to properly licensed landfill sites.

 

2.8     The facility will be equipped with a computer controlled management system, which will regulate and monitor the operation of the plant and all emissions to the environment.

2.9     The plant itself will operate continuously but will only take deliveries of waste during normal working hours.

 

2.10   All the EfW processes are housed in a single building, providing a more attractive appearance and reducing the potential nuisance to neighbours. The building is shown in Figure 2.5. It measures about 139 metres by 101 metres and is a maximum of 40 metres high, with the stack extending to 70 metres.

Materials Recovery Facility

2.11   The Materials Recovery Facility (MRF) will be housed in a specially designed building. It will be of an “L” shaped design measuring 60 x 40 metres and will be located in the north east corner of the site. It will be a maximum of 12 metres high and have a high quality finish designed to match the main EfW building. It will cater for a range of recyclable materials that have been separated by householders from the waste they throw away in their dustbins. This may include glass, cans, paper and cardboard, and possibly textiles, plastics and/or other recyclable goods. Deliveries will take place during normal working hours.

Civic Amenity Facility

2.12   The civic amenity facility is a direct replacement for the existing on-site facility. It will have ten containers for receiving waste and a ramp, up which people will drive to deposit their waste. About half of this waste will be taken to the EfW plant for burning. It will operate the same hours as the existing facility.

Traffic

2.13   Despite the increase in the amount of waste handled, overall traffic flows will increase by less than 7.5 percent, with weekday lorry movements being no more than at present. All traffic will use the existing access to the waste transfer site, off Moorfields Road.

Drainage

2.14   Clean water from roofs will be allowed to soakaway under the main buildings and/or be fed to three ponds that will be built for landscape and nature conservation reasons in the south east of the site. Water from roads and other paved areas will be fed into underground tanks so that any grit or dirt is settled out, before being discharged into the existing sewer to the River Wey through a petrol and oil interceptor. Any polluted water, which has been in contact with waste will be transferred by sewer to the STW for treatment.

Landscaping

2.15   Embankments will be provided on the southern, western and eastern boundaries to blend the new development into the surrounds, to provide visual screening and to assist with noise Where appropriate they will be formed as an extension of existing embankments around the site.

 

2.16   The three types of new planting proposed consist of woodland, rough grassland and wetlands with ponds. In addition, existing woodland located in the east of the site will be retained and protected. The new planting will compliment the existing woodland vegetation located along the northern bank of the River Wey and will consist of native species. As it matures it will help to filter views of the development.

 

2.17   Rough grasslands will provided as a potential source of food to the Barn Owl, which have been identified as feeding on the site. It will be mowed infrequently so as not to lose its wildlife value.

2.18   Finally, ponds will be created to provide additional ecological interest within the site. Rushes will be planted around the margins of the ponds.

Remediation and Construction

2.19   The remediation of the site and the construction of the development will take place over a maximum three year period. The existing transfer station and civic amenity site will continue to operate during this period.

Alternatives

2.20   A number of alternatives have been studied including;

§                     Alternative options for managing Surrey’s waste

§                     Alternative sites for major waste facilities;

§                     Alternative designs for the Slyfield site; and

§                     Alternative access arrangements.

 

The option of doing nothing was also considered.

2.21   In terms of alternative ways of managing Surrey’s waste, the study concluded that recycling and re-use alone could not cope with the volumes of waste that will be generated in future. Even if both increase dramatically, there will still need to be some other form of treating large quantities of waste. Energy from waste is considered better in this respect than the current system of relying upon landfill.

2.22   The study then looked at five possible alternative sites, namely;

§                     Charlton Lane, Shepperton;

§                     Clockhouse Brickworks, Capel;

§                     Copyhold Works, Redhill;

§                     Horley Road, Earlsfield and

§                     Wisley Airfield.

 

2.23   All except Capel are in the Green Belt and so there is a strong presumption in the planning process against them being used for a major waste facility such as an EfW plant. Capel is in the countryside beyond the Green Belt and so is also considered unsuitable to accommodate a large-scale industrial uses. Except for Charlton Lane, all the sites are a long way from where most of the waste originates and so will result in thousands of extra miles being travelled by large lorries each year. Other specific constraints were also found to exist at each of the sites.

2.24   A range of alternative layouts were tested for the application site.  The selected option was found to constitute the most appropriate balance between a range of objectives relating to the way the plant operates, its appearance and the need to ensure that it does not cause nuisance or damage the environment.

 

 

 

 

2.25   Finally, four different ways to access the site were examined.

§                     The existing access arrangement via Moorfields Road;

§                     Direct access onto the A3 through the formation of a new junction;

§                     Formation of a new road linking to Clay Lane in the north west; and

§                     Formation of a new route from the A320 via the existing STW.

 

Of these the existing access arrangement was found to work best and be safest. The other three options were either not practical or achievable or caused environmental or highway problems.

 

2.26   The option of doing nothing will not happen in practice as the site is allocated for employment use. If it were to remain undeveloped, most environmental conditions would remain unchanged except for ground and groundwater contamination, visual appearance and ecology. In all cases the current condition of the site is likely to deteriorate to the detriment of the local environment.

3.       planning policy context

 

3.1     The planning policy context is set out in national, regional and local plans.  The relevant local plans comprise:

 

§                     The Surrey County Structure plan (SSP - 1994);

§                     The Guildford Borough Local Plan (GBLP - 1993.); and

§                     The Surrey Waste Local Plan (SWLP - 1999).

 

3.2     Other policy guidance comprises:

§                     National Planning Policy Guidance;

§                     Draft Regional Planning Guidance and advice comprising RPG9;

§                     The draft Structure and Local Plans; and

§                     The National Waste Strategy (Waste Strategy 2000).

 

3.3     The effect of the development is assessed against this policy background in the remainder of the EIA.

4.       eia context

4.1     The environmental impact assessment considers all environmental effects, positive and negative, arising from site preparation, construction and operation of the IWMC. It looks at the significance of effects and what measures can be put in place to offset potentially adverse effects.

5. summary of environmental impacts

5.1     The following sections summarise the predicted impacts associated with the proposed development according to the main topic areas identified.

6.       geology, groundWATER and surface water

Introduction

6.1     A site investigation was carried out to assess ground conditions and the way in which this affects the groundwater beneath the site. Existing data on the quality of the River Wey were examined, and samples taken from the surface water drain, which flows from the Slyfield Industrial Estate into the River Wey. The data were used to determine surface water quality. Finally, existing data on flood levels were collected to determine if the site contributed to providing storage capacity for flood waters.

6.2               The site investigation found made ground comprising some biodegradable waste and sewage sludge to an average depth over the site of 1.7 metres. Below this are clayey sand and gravels and then the London Clay. The volume of sludge across the site is calculated to be approximately 3,000 m3. Waste materials have been deposited in the past within the site boundary, at the northern end, as part of landfill operations on adjoining land.

6.3               Some contamination was found, particularly from the sewage sludge, where levels of certain pollutants were found to be higher than normal levels in the environment. This is not unexpected given that the land has been used for many years for sewage treatment. However concentrations in the underlying made ground and superficial deposits were below published standards for land used as parks, playing fields, gardens or open space.  The land is therefore suitable for accommodating development without requiring remediation.

6.4     Groundwater quality beneath the site shows low levels of contamination which get worse in the north, suggesting an effect from the historical landfill activities. Testing of the soil for gases proved elevated concentrations of methane and carbon dioxide almost exclusively in areas where sludge has been deposited. There is little evidence of landfill gas coming into the site from the landfill to the north.

6.5     In terms of surface water, the 1 in 100 year flood level has been established for locations upstream and downstream of the site. These are:

§                     At Stoke Mill Farm:                                29.21 m aOD (97.28 feet)

§                     At Burpham Court Park Farm:     26.88 m aOD (89.50 feet)

 

6.6     The quality of the River Wey near to the site is, according to Environment Agency data, shown to be high. As mentioned above, there is an existing surface water outfall from the Slyfield Industrial estate into an ox-bow lake, which forms part of the River Wey. The ox-bow is of much poorer quality.

Construction Impacts

6.7     Due to the setting of the site and its history of development to date, six possible impacts on the environment were identified and assessed:

The loss of flood storage capacity associated with the River Wey

6.8     None of the land proposed for redevelopment is in the floodplain. This means that the development would not reduce flood storage capacity locally. Ground levels have been designed to ensure that no flooding of the site will occur.

A change in the surface water run-off characteristics of the site during remediation and construction works

6.9     The possibility of silt getting washed into rivers always exists when large-scale earthmoving and construction takes place. To protect against this, all surface water will be fed into holding ponds to ensure that any sediment is settled out before clean water passes into the River Wey. As part of the IWMC, a new drainage system will be installed, taking over from the settlement ponds. This will include settlement tanks and petrol/oil interceptors to control the quality of water entering the river.

The release of contaminants in the soil during site redevelopment

6.10   Moving soils around the site may “unlock” contaminants and make them more likely to pass into the groundwater or be released as dust. The level of contamination that has been identified by the site investigation makes the risk of this occurring very low. Furthermore, the possible removal from the site of 30,000 m3of the most polluting material will mean that the long-term likelihood of pollutants passing to groundwater is significantly reduced.

6.11            The risk of contamination will be minimised by ensuring that the area of ground disturbed at any one time is as small as possible and by adopting stringent dust control measures which will be set down and agreed with the Guildford Borough Council in  a “Code of Construction Practice”

 

Excavation into the groundwater

6.12   Excavations in some parts of the site will take place below groundwater. Some groundwater may be polluted Without adequate controls in place, groundwater may be polluted accidentally by spillage. Risks will be minimised by installing temporary sheet piling to reduce the volume of groundwater that enters the excavations. Polluted groundwater that does enter the excavation will be pumped to the adjacent STW for treatment. Groundwater will be monitored throughout operations to check its quality.

Damage to the ecological buffer zone along the River Wey corridor

6.13   The ecological buffer is outside the application site and will not be directly affected by the development. It is important, however, to ensure that it will not be accidentally affected during construction. A stand-off zone will, therefore, be set up to make sure that damage does not occur. Only the raising of the landscaped embankment and the planting of trees will occur within this area. Both will be strictly controlled.

A loss of soakaway capacity at the adjoining Guildford STW during storm events

6.14   Part of the site is currently used by Thames Water as a stormwater overflow. The development proposals will take away this facility. Two factors will ensure that the proposed IWMC will not cause a problem with soakaway capacity: the availability of other Thames Water operational land adjacent to the development site and the potential for process changes at the STW.

Operational Impacts

6.15   The main risks to the surrounding water environment once the facility is operating will occur through:

§                     run-off of water from external areas of waste handling (i.e. the Civic Amenity site);

§                     the potential for spillage of contaminating materials at the site during the period of operation;

§                     the potential for the discharge of fire water run-off into the River Wey during a fire at the site; or

§                     the change in run-off characteristics of the site surface due to the construction of hardstandings, roofs and pavements.

 

All four will be dealt with through the installation of an appropriate drainage system.

6.16   Foul and polluted water will be collected and discharged to the Guildford STW for treatment Clean water from roofs will be drained to soakaways or to the three “ecological” ponds described earlier.

6.17            The remaining water, including drainage from roads and paved areas will be drained to holding/settlement tanks and discharged to the River Wey using the existing surface drain from the Slyfield Industrial Estate.  The drain will be improved to handle the extra volume. A control valve will be fitted to this system and closed off in the event of emergency or spillage.

6.18   Groundwater monitoring will be undertaken throughout the construction period to ensure that no deterioration in quality occurs that might affect the River Wey. Surface water monitoring will be undertaken upstream and downstream of the site to check for adverse effects. Finally, monitoring of soil gas concentrations will be undertaken during and following the removal of sludge material.

6.19   The groundwater, surface water and soil gas monitoring programmes described above will be continued into the operating period of the plant in order to confirm that there is no long term impact on the water environment.

7.       waste management

Introduction

7.1     Three possible impacts were assessed under this Section;

§                     the need to remove spoil or contaminated soils from the site in connection with land remediation and plant construction;

§                     the effect of the development upon the management of household, commercial and industrial waste within Surrey; and

§                     the disposal of ash from the EfW plant.

 

7.2     The volume of non-inert waste that is generated within Surrey is shown on the following table.

 

Table 7.1           Surrey Waste Arisings (million tonnes)

Surrey Scenario

1998 Base Year

Cumulative 1998 – 2010

Household Waste

0.338

5.278

Commercial and Industrial Waste

0.561

6.943

Civic Amenity Waste

0.124

1.770

Total

1.023

13.991

Note: Recycling has been excluded from the figures at this stage and will be discussed subsequently in this chapter.

 

7.3               Surrey also receives waste from, and sends its waste to, other Counties.  If this waste is added in, it means that Surrey will need to treat or dispose of over 18 million tonnes of non-inert waste between 1998  and 2010.

7.4               Some of this can be done through recycling. At the moment, only 9 percent of household waste is recycled. Even if recycling reaches a rate of 25% in line with the target in the Surrey Waste Management contract, it will still leave over 1 million tonnes of waste a year needing to be treated or disposed of by other means.

7.5               Landfill is the only other major option for dealing with large volumes of waste. This will not be able to take untreated waste at current levels once the European Landfill Directive takes effect. So some other form of treatment would be necessary. Also, available space in landfill sites is rapidly running out. Capacity for only about 8.4 million tonnes of non-inert waste existed in permitted landfill sites in 1999 and some of this may not now be usable. Whilst some new sites may be permitted, it is not likely that they can take all the waste requiring disposal up to 2010 let alone beyond this date. The estimated shortfall in landfill capacity, taking account of increases in recycling, but assuming all other things stay the same, will amount to space for about 6 million tonnes of waste.

Construction Impacts

7.6               The only impact during the construction stage comes from the need to remove up to 30,000 m3 of waste. Some of this will need to be taken off site to landfill. The rest, however, can be sorted on site and re-used where appropriate, such as in constructing landscaped embankments.

7.7               There will not be any disruption to existing waste management operations and facilities within Guildford as a result of the switch from waste transfer, using the existing transfer station, to the recovery of energy from waste through a new EfW and Materials Recycling Facility.

Operational Impacts

7.8     The development will result in two main long-term impacts associated with the operation of the IWMC:

§                     A major shift in the management of waste within Surrey through the diversion of non-inert waste from landfill into recycling and energy recovery; and

§                     A requirement to manage the residues from the combustion process.

 

7.9               The first of these represents a major benefit of the development proposals. On its own, the new IWMC will result in a significant increase in both recycling and the recovery of value from waste through the production of energy. Currently 91% of Surrey’s non-inert waste is landfilled. This will reduce to 58% when the IWMC is in full operation and, if the ash is recycled, to only 44%.

7.10            In practice, the plant will not be the only change in waste management within Surrey. It will form part of a comprehensive strategy for managing waste. As part of this wider strategy it will play a major part in reducing the volume of waste going to landfill to only 14%. With associated increases in recycling and energy recovery, this would exceed all Government and County targets for the management of waste. These targets are:

§                     To achieve 45% recovery by 2010;

§                     Within this recovery figure, to achieve 30% recycling by 2010.

Residue Disposal

7.11   The process gives rise to ash that needs to be disposed of. The overall strategy for Surrey includes facilities for recycling bottom ash to make construction materials. Fly ash will need to be sent to landfill. Although this represents a slight adverse effect, this has to be seen in the overall context of the strategy, which reduces the amount of non-inert waste being sent to landfill from 91%to only 14%.

Mitigation Measures

7.12   To minimise adverse effects from the development the following measures will be employed:

 

§                     Re-use as much material on site as possible whilst ensuring that all material that needs to be removed is taken safely to appropriate landfill facilities;

§                     Maintain an efficient combustion process to ensure that the volume of ash is kept to a minimum;

§                     Where material has to be transported off-site, to use the closest suitable facility; and

§                     Reprocess the ash residue where possible.

8.       ecology and nature conservation

Introduction

8.1     The River Wey and its associated floodplain are of high conservation value, due to its location and the species it supports. Parts are formally designated as Sites of Nature Conservation Interest.

8.2               Land between the site and the Wey contains alder woodland and other more scrubby areas containing elder, nettles and giant hogweed. Many of these trees are dying although they still have some nature conservation value for lichens, fungi and use by animals.

8.3               The site itself, however, has been used for the management of sewage sludge from the adjacent STW for at least twenty years. As a result, some contaminants are higher than would normally be apparent in the environment.  Some contaminants have the potential to harm the development of plant communities and affect amphibians. It therefore supports mainly transient plants and few animals.

8.4               Along the north eastern boundary, there are some reasonably mature broad-leaved trees. More mature plant communities were also found to exist both on the sludge lagoons and the surrounding drier land, but no species of importance were noted. Overall, the diversity of plant life is poor, being largely dominated by coarse, vigorous plant species. Most diversity occurs outside the site boundaries, where vegetation is less disturbed.

8.5               Few mammals were recorded on the site, due to the nature and duration of disturbance and the nature of the made ground. It is likely that bats forage over the site, roosting in adjacent trees.

8.6               A reasonable number of species of bird have been recorded on the site. The most significant of which is the barn owl, which was recorded as foraging over the site, but not nesting or breeding.

8.7               Reed bunting was also seen foraging on the site and are likely to be associated with the extensive marshland on the opposite bank of the river. Other seed-eating birds also feeding on the site include goldfinch, chaffinch and house sparrow.

8.8     In summary, the site has been subject to continuous disturbance and deposition of sewage sludge. The habitats found on site are common and are not of real conservation value. However, their location near high quality habitat does increase their potential contribution towards local biodiversity.

Construction Impacts

8.8               Construction activity will lead to the direct loss of the habitats on site, except for the stand of woodland at the northern end. This will, however, be disturbed in part as a result of the need to upgrade the surface water drain.

8.9               The loss of foraging for barn owls, even for a temporary period, is a potentially undesirable effect of development. However, the limited contribution of the site to their feeding requirements means it is unlikely to be important. The final design for the site makes specific provision for foraging areas and perches for barn owls and so will improve the position in the medium and long terms.

8.10   Species such as reed bunting, snipe, green woodpecker, goldfinch, blackbird, dunnock and starling will lose some foraging habitat. Of these, only blackbird and dunnock are likely to nest on the site. Both foraging and nesting will, however, return after construction and so any effect is only temporary.

8.11   Construction operations will result in increased noise and human activity and this may cause disturbance to birds and animals. However, those on site or nearby will already be accustomed to noise from the WTS and CA site and hence the effect will not be significant. Vibration associated with construction is predicted to be of a similar level to normal footfalls at the River Wey and so again will have no detrimental consequences. Retention of the corridor along the bank of the River will ensure that no important wildlife corridors are affected.

Operational Impacts

8.12   The most important impact from the operation of the IWMC stems from possible air pollution effects. It may effect ecology through:

§                     Direct deposition of pollutants on leaves or soil;

§                     Deposition of pollutants on soil or water leading to build-up in the habitat; and

§                     Contribution to acid rain.

 

8.13   Predicted emissions from the EfW plant are extremely low and are well within guideline levels and so there is no evidence to suggest that harm will be caused to plant or animal communities as a result.

8.14            In terms of important or sensitive areas, there are 16 Sites of Special Scientific Interest within 10km of the proposed site. Of these, only Whitmoor Common SSSI lies within the zone where the deposit of pollutants is likely. It lies at the extreme edge of this zone and so any impacts are likely to be negligible. However, there may be a slight increase in deposition of pollutants, which over time could lead to acidification of both the heathland and in particular Britton Pond.

8.15   Lichens are particularly sensitive to changes in air pollution levels and there may be an effect on them even though emissions from the plant are very low. Again, however, three is no evidence avialable that this will be the case.

 

Mitigation Measures

8.16            Overall, the effects on ecology are not significant. Indeed the removal of contaminants from the site is likely to have a beneficial effect on surrounding habitats. However, it is still possible to improve ecological interest as a result of the development. The main measures proposed are;

§                     Providing grassland areas and perches for foraging Barn Owls;

§                     Creation of three new pond areas as permanent aquatic habitats; and

§                     Landscaped planting designed to be sympathetic to ecology needs.

 

8.17   In addition, it may be possible with the agreement of the landowners to improve the Ox-bow lake to the north east of the site in association with the provision of new site drainage. Although not necessary to offset the effects of development, it does represent a chance to contribute to enhancing ecological habitats in the area.

9.       air quality

Introduction

9.1     The main tool used to assess the air quality effects of the development is that of dispersion modelling. This predicts the concentration of pollutants given out by the EfW plant and, based upon chimney height and “worst case” weather conditions, how these will be dispersed in the atmosphere. Other effects looked at include dust from construction activities and emissions from traffic.

Construction Impacts

9.2               The main air quality issue during the construction phase is the generation of dust through remediation and construction operations. These impacts are no different to those experienced with any major construction project and are easy to control using well established construction management techniques.

9.3               Impacts will be controlled through a “Code of Construction Practice” which will be prepared and agreed with the Guildford Borough Council before works start on site.

Operational Impacts

9.4               The main pollutants released into the atmosphere from the process will be combustion products, such as carbon dioxide, sulphur dioxide and nitrogen dioxide. In all cases, the level and concentration given off are well within emission regulation limits laid down by the European Parliament and implemented by UK law. For example, the level of sulphur dioxide given off represents only 0.6 percent of the relevant air quality standard. The comparable figure for nitrogen dioxide is 3.8 percent. For dioxins and furans the figure is as low as 0.03 percent.

9.5     The results of dispersion modelling for all pollutants indicate that the design of the plant will ensure that any emissions from the stack are harmless.

9.6     Carbon dioxide is not harmful to health but is a greenhouse gas. The use of EfW will result in an overall decrease of CO2 emissions to air by reducing the burning of fossil fuels to generate electricity and the production of methane from landfill sites.

9.7     The level of change in traffic on the roads as a result of the development is negligible. So, therefore, are the potential air quality impacts. The assessment shows traffic will have no significant impact on background air quality concentrations.

9.8     As well as simply looking at emissions from the plant itself, the assessment also looked at the cumulative effect; that is the existing background concentrations in combination with the additional contributions from traffic and process emissions. This found that pollutant levels remained well within the relevant emissions standards.

9.9     The air quality assessment also looked at the health effects of the long-term operation of the plant. In summary, it found that the potential impacts of the IWMC operation on the health of the local population, even under a worst case scenario of lifetime exposure, would not be significant. In all cases, the worst case daily intake of contaminants would remain well below that which occurs naturally in the UK population from background sources.

10.     noise

Introduction

10.1   Noise surveys were carried out in the area to establish existing background noise levels in order to compare these with forecasts for the proposed development. As the EfW plant will operate on a continual basis, readings were taken for day and night-time.

10.2   These surveys found that the area is relatively noisy due to the proximity of the A3. It is likely that traffic will increase rather than decrease in the future and there is likely, therefore, to be a gradual increase in background noise level for the area. Local traffic within the estate is also likely to grow and add to this.

 

Construction Impacts

10.3            Most construction operations do not generate large amounts of noise and would rarely be heard at nearby houses. Piling will be required, however, and would give rise to vibration. This will not be felt at the nearest houses. The noise from pile driving is likely to be heard but will be below the level that Surrey County Council have specified in the guidelines for temporary operations and well below the limit normally accepted for construction and demolition noise.

10.4   This will be controlled through a “Code of Construction Practice” which will be prepared and agreed with the Guildford Borough Council before works start on site.

10.4            The temporary increase in vehicle movements during construction is well below the level at which the Department of the Environment, Transport and the Regions would require assessment.

Operational Impacts

10.6   Noise sources within the plant need to be considered during both day and night as the plant will need to operate continuously. Other sources such as vehicle deliveries and the operation of the CA site will only take place during the day.

10.7   No operational site activities will generate vibration that would be felt outside of the site boundary.

10.8            To meet SCC guidelines, the plant has been designed to ensure that the noise levels generated are below the level that could be heard at the nearest housing at the quietest part of the night or day. This has meant placing many of the noisier operations inside a single building and using silencing on other parts of the process. This applies to the fans and condensers needed to cool the air and draw it up through the stack for high level dispersion.

10.9            As a result of employing these measures, the worst case noise prediction falls below the SCC criteria for night-time noise, meaning that the plant will not be heard at the nearest houses. In practice, noise levels will be lower than predicted.

10.10  The changes in traffic flow on all roads as a result of the development are well below the level at which the Department of the Environment, Transport and the Regions and the Institute of Environmental Assessment considers an assessment is normally required.  For all of the roads, the changes in noise level are negligible and hence no noise level increase would be noticeable.

 

11. traffic & transportation

Introduction

11.1            The proposed access for the new development is the same as for the existing WTS and CA site, namely off the A320 via Moorfield Road. A comparison was therefore undertaken to assess whether the development would increase the levels of traffic on these roads, and if so whether that increase would have any adverse effects.

11.2            The existing waste transfer operations generate on average 1,320 heavy goods vehicle movements during weekdays and 34 on Saturdays. These figures were obtained from traffic counts. In addition there are cars visiting the CA site.  Peak hour flows for weekdays, which is when most traffic on the roads occurs show only 19 movements in the morning and 2 in the evening.

11.3            The survey demonstrated that queues occur along Woking Road during peak hours, particularly between the Moorfield Road and Hazel Avenue, however, this will improve with the installation of traffic lights at the Moorfield Road junction.

Construction Impacts

11.4   With the possible exception of the major concrete pour, the construction phases will not result in any material increase in the levels of heavy goods traffic on the local highway network. The worst phase was assessed to determine the affect upon queues during peak hours and was found to have no significant effect, with a 2.5 percent increase in traffic during morning and evening peaks on Moorfield Road itself and only 1 percent on the A320 southbound.  This phase will in any event last for a maximum of only 8 months.

Operational Impacts

11.4            It is estimated that when fully operational the development will generate 1,280 heavy goods vehicle movements during weekdays with a total of 84 on Saturdays. The weekday totals equate to the volume of heavy goods vehicle traffic currently visiting the site. An increase in the workforce will mean corresponding increases in car movements of 30 movements per day but this will have no effect upon the operation of the road system. The number of Saturday movements will increase by 66 of which 16 will be cars and the remainder heavy goods vehicles. This again is not significant in terms of the operation of surrounding roads.

11.5            In terms of the peak flows, the morning weekday peak will increase by only 3 movements, whereas the evening peak will decrease by 2 movements with no projected movements occurring.

11.6   In conclusion, the site access will experience a slightly higher level of traffic on a Saturday, however, this is not considered to represent a material impact for a junction that does not suffer any congestion or queuing. Operations will not lead to a worsening of the situation on the A320 due to the minimal increase in vehicle movements forecast. A lorry routing agreement will be entered into to make sure Heavy Goods Vehicles use only the major routes and this will represent a gain as a result of the development.

12. cultural heritage

Introduction

12.1            Cultural Heritage covers both archaeology and the possible effects on the conservation area of the River Wey.

12.2            Archaeological interest was assessed by looking at a wide range of records, including old maps, and by studying aerial photographs. The records show a number of archaeological finds within the area of the application site from neolithic, bronze age, iron age and Roman periods. No archaeological features were discernible in any of the aerial photographs studied.

12.3            The River Wey conservation area was designated as recently as 1999 and is tightly drawn to include only the navigation itself, the towpath and important structures alongside it.

Construction Impacts

12.4            Any excavation and movement of sludge and soil during construction may cause potential damage or destruction to any surviving archaeological features or deposits or finds which may exist within the site. However, it is possible that such damage has already occurred during the original construction of the sludge beds.

12.5            Field evaluation in the form of trial trenching or a watching brief will therefore be undertaken during construction works. The advice of Surrey County Council Archaeology Section will be sought in establishing the scope and specification of further archaeological work.

Operational Impact

12.6            There are no anticipated effects to archaeological deposits from operations on the site.

12.7            The character of the River Wey corridor, and hence its interest, is not dependant upon views over the application site. Furthermore, it is compromised near to the site by the effect of the A3, pylon lines and the industrial estate itself. Therefore the development will not cause harm to the setting of the conservation area.

13.     socio – economic effects

Introduction

13.1   The development will result in the creation of both temporary construction jobs and increased levels of permanent employment on the site with around 55 new jobs being created.

13.2            In terms of construction employment, beneficial effects will occur over the three years that the development will take to build. The maximum number of construction workers forecast to be working on site in any one month is around 320. The average number of workers on site during the construction phase will be 135 workers.

13.3            The development will increase employment over ten fold compared with the existing waste transfer operation. It will require a range of skills and the operators will offer training to help provide appropriate skills to people within the local labour market.

14. land use, recreation and amenity

Introduction

14.1            The effect upon land use and amenity within the area will depend largely on the conclusions of other sections of the assessment such as the assessments of noise, air quality and traffic. The way in which these effect local communities was therefore studied. Consideration was also given to how the development would affect people’s recreation opportunities and enjoyment of them.

14.2            The local community living near the Slyfield Industrial Estate is already affected to a degree by it and by the noise that originates from the A3. Uses surrounding the site include the Guildford STW, a builders merchant and the existing WTS and CA site. More recent improvements have come about through the introduction of smarter car showroom uses but these have not changed much the general industrial nature of the estate. The Riverside park is an attractive recreation area but is also affected by the A3, the pylons that cross the area and the industrial estate.

Construction Impacts

14.3   The local community will be slightly affected by construction operations although the use of a strict “Code of Construction Practice” which is enforced by the Borough Council will ensure that no significant effects occur. There will be no direct effects on the community such as loss of existing facilities. All effects that are felt will therefore be indirect, limited and temporary.

Operational Impacts

14.4   The development will not require the closure or removal of any existing facilities although once the IWMC is completed, the existing WTS and CA facilities will no longer be required and could be removed from site.

14.5   The development accords with the planning policy in the Surrey County Structure Plan, the Guildford Borough Local Plan and the Surrey Waste Local Plan and therefore represents an appropriate use of the application site.

14.6            The development will be visible from some sections of the towpath, the River Wey and the Riverside Park and may therefore reduce some peoples’ enjoyment of these areas albeit not by a great deal. Other footpaths will not be similarly effected as they are already much closer to the industrial estate and have clear views of it.

14.7            Existing uses on the estate will not be affected as the development is a replacement for the existing WTS and CA facility in a similar location and of an improved appearance.

15. landscape and visual assessment

Introduction

15.1            The effect of the IWMC on both the local landscape and on views from important viewpoints forms an important part of the environmental assessment.

15.2            A balloon was flown over the site, representing the height of the stack and photographs taken from a wide area of Guildford and its surrounds to assess how visible the plant would be. This enabled a computer image of the plant to be accurately positioned within photographs in order that its effect from key viewpoints could be seen.

15.3            The site is described by the Countryside Agency as part of the “Thames Basin Heath” landscape which is characterised as a diverse landscape with open, rolling heathland and conifer woods providing some unity. Heavily populated areas also exist with development focussed in transport corridors. River valleys are broad with gently rising sides and a complex pattern of canals, ditches and channels with undrained areas in the valley bottoms.

15.4            The site takes its character from the series of sludge lagoons and treated sewage spoil heaps, which dominate the site. Most of the mature vegetation is on land around the site, not the site itself.

15.5            The site is also influenced by the character of the industrial estate and the River Corridor. These are in marked contrast to each other. The estate is generally unattractive with no overall theme and dominated by clutter such as parked cars, open storage, signage etc. Some improvement has been achieved through new developments and the Borough Council is keen to see further improvements to the estate as a whole.

15.6            The River corridor is generally attractive with an enclosed feel resulting from mature trees that prevent long distance views.  There is considerable ecological interest, mainly to the east of the river, with extensive reed beds, open water and unimproved grassland. The landscape quality is affected, however, by the A3, the electricity pylons and the industrial estate.

 

Construction Impacts

15.7   Any impacts during the construction phase will be temporary but will tend to have an adverse effect whist they last.

 

 

Operational Impacts

15.8   Guildford’s urban form is of low-rise development interspersed with large built forms including the cathedral, the shopping centre, the university and the leisure centre.  The development will be in keeping with this landscape forming an additional large built form on the urban fringe adjacent to an industrial estate.

15.9   The smart design and high quality materials used for the new plant will actually result in an improvement of the local character of the industrial estate. Whilst it will be more visible than the existing WTS and CA facility, the use of curves in the design of the building, particularly within the stack, will make it look less industrial and therefore will be seen as a more attractive element in views.

15.10  The plant will also assist more local views, with the current derelict appearance not only of the site itself but also of the existing WTS and CA facilities giving way to a modern landscaped development.

15.11  The landscape character of the river corridor is protected by the existing belt of trees which provides screening of the site and enclosure of the river. The tree belt will be reinforced by new screen planting within the site. Therefore the effect of the development on the River Corridor will be low.

15.12  Views from surrounding housing areas will vary, with most being obscured by other houses and vegetation. It is likely therefore that the EfW plant will only be glimpsed from the majority of locations within existing estates.

15.13  In summary, the form of the building, site layout, the use of landscaped embankments and the extensive planting of native trees all contribute to reducing the visibility of the development. The IWMC will not therefore adversely affect the landscape character of the area or the quality of the landscape. Neither will it result in unacceptable levels of visual intrusion in either the night or day.

Return to top

Return to Information